How long it takes.

How long it takes to get a sauna, from order to first session.

Most garden saunas go up in one to four days. The wait before that is the long part: from a few days for a sauna in stock to six months for a bespoke build. Here is a realistic timeline, and what dozens of sellers say about their own lead times.

Updated · 6 min read

Generated sauna scene: a wood-burning stove topped with stones, beside a wooden bucket and ladle.

How long it takes, from first look to first session

  1. 1–2 weeks: decide and quoteChoose the type and size, check planning and your power supply, get written quotes.
  2. Days to 12 weeks: lead timeIn-stock saunas ship in days. Made-to-order saunas usually take 4–12 weeks. Bespoke builds can take 3–6 months.
  3. 1–2 weeks before delivery: prepareLay the base and let concrete cure; have the cable run or the flue position agreed.
  4. 1–4 days: installMost garden saunas are assembled in a day or two; cabins built from panels in two to four working days.
  5. Same week: connect and certifyYour electrician connects the heater and certifies the work. A wood-fired sauna needs a first, gentle burn.

What sauna sellers say about lead times

These are the lead times 42 sellers give on their own websites. They change with the season: spring and early summer are busiest, so order in autumn or winter if you can.

What sauna sellers say about lead times, checked 22–29 October 2026
SellerWhereWhat their website says
Aquasun IrelandIrelandUsually 2–4 weeks for stock, longer in busy seasons; up to 12 weeks if the sauna is not in stock in Ireland (Hiki L page) source
Ardinagh Home & LivingIrelandSaunas are made to order; approximately 4–6 weeks from order date (stated on barrel sauna product pages) source
Caragh NurseriesIrelandAverage 4 weeks for delivery and installation of the Lighthouse Sauna; may run a week or two over in peak times source
Irish Sauna CompanyIrelandApproximately 7–8 weeks for mobile saunas (product pages say about 6–8 weeks); 50% deposit secures a build slot source
LoghouseIrelandGiven as guidance only; 8 to 12 weeks or more at busy periods (general terms, not sauna-specific) source
Nordic SaunasIrelandInstallation of a 4 seater, including foundations and electrics, typically takes three to four days on site. Lead time from order not stated source
Polaris SaunaIrelandAverage 6–8 weeks; custom products may take slightly longer. Pre-configured Luna, Lyra and Vega approx. 8–9 weeks. The 2.4 m Comfort Cube in stock has no production lead time. source
Revival Health LabsIrelandBarrel saunas 2 to 4 weeks; cold plunge tubs about 5 weeks; accessories 3 to 7 business days (estimates, may vary in autumn and winter) source
Sauna GuysIrelandMost projects 2–4 weeks, including design, build and installation (varies with design and size) source
Sauna IrelandIrelandIn-stock models dispatched the day after order, delivered within 1 to 5 days (The Snug product page) source
TimbertroveIrelandNot stated for saunas. General delivery and fitting: about 1 to 3 weeks, 4 to 6 weeks at peak times source
Aqualine SaunasGreat BritainIn-stock SaunaMed saunas dispatched the same day if ordered before 3pm; other items per product listing (Harvia outdoor saunas listed at about 10 weeks) source
Backyard SaunasGreat BritainA typical 3–4 person build takes around 16 days of work source
BaltoScandiaGreat BritainBarrels, cubes and log saunas 12–14 weeks; modular saunas 14–16 weeks; bespoke add 1 week (updated April 2026). Hot tubs and ice baths 2–3 weeks. source
Calido Logs & StovesGreat BritainSaunas: 4 to 12 weeks from order. Cold tubs: usually 3 to 4 weeks, or 6 to 8 weeks if shipped from Finland source
DoonGreat BritainSaunas typically 8 weeks from the start of fabrication (cabins typically 16 weeks); confirmed once a build slot is secured source
Dorset SaunasGreat BritainAround 12 weeks (varies with demand) source
Finnmark SaunaGreat Britain3 to 10 working days for most products; sauna cabin times vary and special-order lead times apply source
Full Circle SaunasGreat BritainReady-designed models can be delivered in as little as 6 weeks source
Greenhouse StoresGreat BritainPalmako saunas: within 4-6 weeks; Lichfield Crown Elegant: within 10-12 weeks source
Hamalainen UKGreat BritainDelivery dates approximate; customer told and offered cancellation if delivery will exceed 28 days source
Heartwood SaunasGreat BritainNot fixed; varies with the workshop schedule, ask for current timing source
Heracles WellnessGreat BritainStock sauna kits: delivery in 3 to 5 working days from the Essex warehouse. Made-to-order Camilla versions: around 4 to 6 weeks. Leil Round Cube: about 6 weeks production (8 weeks for mirror glass). Saunum cabins are made to order in Estonia source
Kingsbury Sauna CoGreat BritainVaries with customisation; a timeframe is given at the point of order source
Kirami UKGreat BritainManufacturing 4–8 weeks depending on time of year and products; shipments leave Finland every 2–4 weeks source
LeisurequipGreat BritainBespoke saunas usually 4–8 weeks from first consultation to completed installation (longer in areas such as northern Scotland). Harvia shop items usually in UK stock, otherwise 3–6 weeks direct from Harvia. source
Morgan Garden StudiosGreat BritainDelivered as pre-made panels and built on site in 2–4 working days; price guide says complete in one to two weeks. Start date fixed at booking. source
Nuovo LuxuryGreat BritainGenerally 2–4 days for delivery, varying by brand and product; indoor infrared KY004 3–5 working days source
Oceanic SaunasGreat BritainProduction lead times (updated 13 Oct 2026): domestic Finnish and infrared cabins 6–7 weeks; commercial cabins 6 weeks; outdoor cabins 12–14 weeks; Turkish steam rooms 4 weeks; then a 7–10 working day delivery network source
Out of the ValleyGreat BritainCurrent lead time 3–6 months; larger custom projects may take longer source
Outback365Northern IrelandTypically shipped within 12 weeks of order; varies by model and options source
Palmako UKGreat BritainUntreated: 2–4 weeks; dip-treated or painted: add 3 weeks (Anita M; some models such as Grace S and Astra L show 6–8 weeks) source
PlankbridgeGreat BritainBuilt to order; lead time varies with specification and the build schedule, call for the current timeframe source
Sauna BoxGreat BritainNo fixed lead time; quoted against the customer's opening date. Build times listed per layout: 12 days (10 ft container), 20 days (20 ft container), 22–23 days (horsebox) source
Sauna StableGreat BritainMost builds completed within 8–10 weeks (a summary strip on the same page says 10–12 weeks typical) source
SaunaShopGreat BritainUsually dispatched within 2 working days and delivered inside a week; non-stock items 10 to 14 days source
Scottish SaunasGreat BritainAround 6 to 9 weeks for an outdoor barrel sauna to arrive (barrel product cards say 7 to 11 weeks) source
Shokk&AweGreat BritainWestwood 5–7 weeks; Gstaad from 6 weeks; Småland 3–6 months source
Skotlanti SaunasGreat BritainTypically a couple of weeks from design sign-off to installation (bespoke), depending on specification; exact timings confirmed with the quote source
Summerhouse24Great BritainDelivery estimation 3 to 5 weeks for sauna cabins (barrel saunas and pods show 6 to 10 weeks on their pages) source
TuinGreat BritainUsually 2-3 weeks; a delivery period of 1-6 weeks can be chosen when ordering source
Urban Ice TribeGreat BritainDispatch within 2 working days; delivery 5–10 working days for standard orders, 10–14 working days for bath and chiller set-ups and large deliveries source

What slows things down

  • Planning. If your sauna needs permission, add the council’s decision time. In Ireland the planning authority generally has eight weeks from a valid application,1 and in England most applications have an eight-week time limit,2 longer if more information is asked for or there is an appeal.
  • The electrician. Book early: a long cable run, a new fuse board or a three-phase upgrade can take weeks to arrange.
  • Access. A prebuilt sauna that needs a crane depends on the crane’s diary and a dry day.
  • Cross-border delivery. Freight between Great Britain and Ireland adds customs paperwork.
  • Custom options. A different timber, a glass front or a changing room can add weeks.

How we wrote this page

Prices, sizes and lead times come from each seller’s own website. Every one links to the page we read, and we last checked them on 22–29 October 2026 for the Olladay sauna industry directory. Prices are the lowest listed for that product, before delivery, base and electrics unless the seller says otherwise, and can change at any time. Lead times are quoted as each seller states them; some describe manufacture, some delivery and some the whole project. Spotted something wrong, or sell saunas and want your prices checked? Email us.

Olladay makes booking software for saunas. Nobody pays to be listed or ranked on these pages, and the tables are in price order, not in order of preference.

Next steps

References

  1. Dublin City Council. Planning application timelines. www.dublincity.ie/planning-and-land-use/make-planning-application/planning-application-timelines
  2. Ministry of Housing, Communities and Local Government. Determining a planning application (England). www.gov.uk/guidance/determining-a-planning-application

Questions

How long does it take to build a sauna?

Installing a garden sauna takes one to four days on site. The wait before that is longer: in-stock saunas ship in days, most made-to-order saunas take 4–12 weeks, and bespoke builds can take three to six months.

How long does a barrel sauna take to assemble?

Usually a day for two people with the instructions, or a few hours for the seller’s fitters. Allow longer for a porch, roof shingles or a wood stove flue.

When is the best time to order a sauna?

Autumn and winter. Lead times are usually shortest then, and the sauna is ready before spring, when demand peaks.

Can I use my sauna straight away?

An electric sauna can be used once the heater is connected and certified. Follow the heater maker’s first-heat instructions; a wood stove usually needs a gentle first burn to cure its paint.

Related

Opening your sauna to the public?

Olladay takes bookings, payments, health terms and weather closures for saunas in Ireland and the UK. Your sauna pays nothing to start.

See sauna booking software

Want to try a few saunas before you buy one? Find a sauna near you.